I was recently working with a company who didn’t
understand the difference between proactive and reactive risk management on
product development projects. Oh sure,
they could explain the concept in a meeting, but their business practices told
a different story.
First, let’s acknowledge that we need
both. Proactive risk management can
avoid and minimize risks. But sometimes
the unexpected happens and we need to respond to it when it does. A strong risk management approach will
periodically assess the project to identify risks and proactively take actions
to avoid and mitigate negative risks while enhancing and leveraging positive
risks. And at the same time, the risk
management approach will be constantly assessing progress and variances – both technical
and project progress – to determine when unexpected conditions have occurred. An analysis of those conditions will lead to
appropriate corrective actions or responses.
Risk Events
Let’s look at the attributes of proactive
and reactive risk management, at least as they apply to technology or product
development project. Risk is defined by
the Project Management Institute as, “An uncertain event or condition that, if
it occurs, has a positive or negative effect on one or more project objectives.” There are three aspects I want to
highlight. First it is an uncertain
event. Second it can be both positive
and negative. And third, it effects on
or more project objectives.
Proactive risk management focuses on
identifying the uncertain events and estimating the effects of the
objectives. Reactive risk management
starts with the unexpected effects and attempts to determine the events that
caused those effects. In both cases,
actions are taken to protect the project goals.
However, in proactive risk management, an action is taken to avoid or
prevent a negative effect or to enable or enhance a positive effect. In contrast, with reactive risk management an
action is taken to recover or compensate for the already existing unexpected negative
effect on the goal or an action is taken to lock in the benefits from an
already existing unexpected positive effect on the goal.
Effective risk management needs to include
both proactive and reactive elements. It is obvious that if you don’t do
either, disaster is likely to strike your project. But even if you do one, but not the other,
disaster is still likely to strike. Let
me illustrate using the experiences of the company I mentioned earlier.
Proactive without Reactive Risk Management
This company did proactive risk management
for project risk events. They conducted
a risk analysis shortly after the project started where they considered a
variety of project risk events that could affect the project. These included schedule issues, resource
issues, and some technical issues. The
risk analysis was captured in a risk register, proactive risk responses were
identified and most were implemented.
And that was the last time that project risk was discussed on the
project until the accumulating disasters caused the project to be cancelled two
years later.
Proactive risk management was done and the
actions taken were good ones. But the company
and project team did not regularly assess project performance with respect to
cost and schedule goals. They just kept
changing the schedule and throwing resources at problems. There
were ample signs that other unexpected events had occurred and that the project
plan and project approach was not working.
However, the project team did not stop to assess what was going on and analyse
the project to determine the root cause or causes of the risk events. Therefore they never took appropriate
corrective actions. Finally two years
into the project, they were approximately 18 months behind to the original
schedule and the spending was nearly double the original budget.
Reactive without Proactive Risk Management
While the company did proactive risk
management with respect to project goals, they did not do any proactive risk
management with respect to technical goals.
This was a development project using emerging technology and it was
pushing that technology to an order of magnitude improvement in several of the
key technical performance characteristics.
In addition, the product was evolving from a complex mechanical product
to a system involving complex mechanical elements, electronics, software, and systems
integration with other customer systems.
The project team did not do any proactive technical risk
assessment. In fact technical risk was
never discussed in their project reviews – just technical problems.
The technical problems were addressed using
a reasonable and effective reactive risk management approach. As a problem was identified, a root cause
analysis was performed and a solution was created to solve that problem. But since no proactive risk management was
done, the solutions often then created even more technical problems. And when a technical problem was finally
solved, it would just unmask the next technical problem. The project went through a continuous set of
technical problems and issues, with the result that despite dozens of systems
being constructed, none of them was ever fully compliant with the specifications. Finally, after two years of work, the design
team reported to management that the current design approach was not robust
enough to ever meet the customer’s use requirements. If the
company wanted a product that would be satisfactory to the customer, they would
need to restart the development project with an entirely new concept.
Combining Proactive and Reactive
Risk Management
If the company had effectively combined
both proactive and reactive risk management approaches around either the
project or technical goals, the situation would have been recognized much sooner
and the project could have been salvaged.
The proactive project risk management made some good project
enhancements. If it had continued to
monitor for risk, it would have identified that something wasn’t right with the
technical approach and corrective actions could have been taken. The reactive technical risk management
continually fixed one problem after another, but a proactive analysis would
have identified that the fundamental concept was too risky and a different
approach would have been used.
The lesson for project managers is to do
proactive risk management early in the project.
And then monitor performance, identify variances and do effective root
cause analysis as the project progresses.
These complementary approaches should lead to project success.
Thanks for this post. It is very important for a small business
ReplyDeleteRisk Management Services
Proactive and reactive risk management are two approaches to identifying and handling risks in projects or organizations. Here’s a breakdown of each:
DeleteProactive Risk Management
Definition: This approach involves anticipating potential risks before they occur and implementing measures to mitigate them.
Key Characteristics:
Risk Identification: Regularly identify and assess risks through techniques like brainstorming, SWOT analysis, and risk assessments.
Preventive Measures: Develop strategies to minimize the likelihood and impact of risks (e.g., training, process improvements).
Monitoring: Continuously monitor the environment for changes that may introduce new risks.
Documentation: Maintain detailed risk registers and action plans.
Benefits:
Reduces the likelihood of risks occurring.
Enhances preparedness and responsiveness.
Promotes a culture of risk awareness within the organization.
Reactive Risk Management
Definition: This approach addresses risks after they have occurred, focusing on damage control and recovery.
Key Characteristics:
Response Planning: Develop contingency plans for identified risks, focusing on how to respond once a risk materializes.
Crisis Management: Implement crisis management protocols to address immediate threats.
Review and Learn: Analyze the impact of risks that have occurred to improve future risk management practices.
Benefits:
Provides a clear response framework in case of unforeseen events.
Allows for real-time adjustments and learnings from incidents.
Can be effective for risks that are difficult to predict or control.
Big Data Projects For Final Year Students
Image Processing Projects For Final Year
Deep Learning Projects for Final Year
Nice Information about risk management.
ReplyDeleterisk management
Creative and informative articles
ReplyDeletefederal sex crimes washington DC
dc sex crimes lawyer
Interesting blog thank u for sharing informative blog IT Risk management services
ReplyDelete