Thanks to the Corona Virus, many people are suddenly forced to work from home. Here are some tips to make that transition smoother.
Showing posts with label Project Management Methodology. Show all posts
Showing posts with label Project Management Methodology. Show all posts
Monday, March 16, 2020
Monday, April 18, 2016
Pivoting Project Management Reviews
Entrepreneurs are using the terms “pivot”
and “persevere” to identify strategies for decision-making. When confronted with a situation that is not
leading to the desired results, they must decide whether to gut it out and
persevere on the current path, or pivot to a new direction and new
approach.
This decisions process can and should apply
to many of our business and project management practices. If your practices are not leading to the desired
results, make a conscious decision to pivot or persevere.
Let’s talk about the project management
practice of project reviews by senior management. Are the reviews leading to better project
execution and performance? Are the reviews
leading to better project selection and planning? Are the reviews leading to better project
portfolio performance in terms of business impact? If the answer is, “No,” and you have been
doing the same types of reviews for years, it is probably time to pivot.
Project Management Reviews
Let me describe the typical project
management review I see when I first visit a new client. Senior management is reviewing project status on a
regular basis – normally tied to the calendar.
For example, one client had a weekly review a summary of all open
projects and a “deep dive” on two or three projects based upon which projects
were perceived to be in the most trouble.
At the deep dive portion of the reviews, the emphasis was upon the status of the problems or issues that had occurred and what the team was doing
about those issues. The project team received
lots of “help” to fix the current problem, but there was seldom any discussion
about extrapolating from the current issue to foresee future issues or to share
lessons learned from this situation with other project teams so that they could
avoid the same problems.
My recommendation for a project management review pivot is to
change from this backwards-looking, reactive project management reviews to a
forward-looking preventive project review.
What do I mean? The project
review should be focused upon all the open and remaining risk threats on the
project (not just the current crisis) and the resources and management actions
needed to reduce or eliminate those threats.
And when you get that working well, add a discussion about the possible
risk opportunities for the remainder of the project and the resources and management
actions that will enable those opportunities to be realized.
Superman
The current approach leads to a “superman”
mentality among project leaders. They
bounce from crisis to crisis, using their superpowers to overcome each
one. They don’t prevent problems, they
just solve them. The leaders get great
credit and often rewards for their effort.
In fact they often take on “rock star” status within the
organization. While they may be good
fire-fighters, I would not call them good project managers.
Let me relate a story from a client of
mine. His high-tech firm had two major
development projects underway. Both were developing new product lines using emerging technology.
Both projects were large be this company’s standards – they were planned
for three to four years in duration, with a budget of over $20 million, and a
large team located in multiple sites.
Both projects were managed by senior project leaders with strong
technical, business and inter-personal skills.
One project leader, we will call him Jack,
was a fire-fighter. His team faced many
problems and challenges and he overcame all of them. Granted it took late nights, weekends, and
some creative solutions but with his charismatic personality he rallied the team and they come through. The project was a major market
success. However, the project finished more than a year late and several million dollars overrun.
The other project leader, we will call him
Dave, was a risk manager. Dave
emphasized proactive risk management. He
had a well-developed plan with risk triggers and options that were used by the
team. His project did have several minor
fires that had to be resolved, but nothing like the problems that occurred on
Jack’s project. Dave also had a major market success.
But Dave’s project was only two months late and came in on budget.
So now it is six months later and the
business is going through a major restructuring due to some problems in a
different division. The business is
downsizing and it only needs one senior project leader. So Dave was laid off. I asked the senior management why they laid off
Dave instead of Jack. Their response
surprised me. In their opinion, Jack was
a superhero who could fix any problem, but they didn’t know if Dave could
handle the stress of a major project in crisis.
I pulled together a summary of the two
projects, including the major challenges that each had to overcome. I identified the proactive risk approaches
that Dave had used and the absence of those in Jack’s project. Several of the senior managers told me they
had never stopped to consider the risk management approach in the project
reviews. They never asked about risk
avoidance and mitigation. They were just focused on the current crisis and what
was being done to fix it.
The Pivot
So if you want to transform your project
performance, I encourage you to consider pivoting your project management
review approach. When reviewing a
project, I recommend the following topics.
- Quick review of the Project Charter. Remind everyone of the project’s purpose and goals.
- Current status with respect to the project plan. Make sure the team is reporting against the plan and don’t just give a list of the things that they have been doing. If they aren’t working the plan find out why.
- Risk issues with their response or mitigation strategies that should be encountered or resolved within the near future. Ensure the team has an adequate strategy and resources to resolve the risks.
- New risk issues that have been discovered since the last review. What changed to create these risk issues and what other impacts could those changes have on the project.
- Critical milestones and decisions that will occur on the project in the near future. These are potential risk points and senior management may want or need to engage with those activities.
Changing your project management reviews
into risk reviews will pivot your project management approach from reactive to proactive. I can assure you the project performance and
business impact will improve. But some
of your superhero project leaders may resist the change. They are fire-fighters and want a fire to
fight. Risk based project reviews will suppress fires and expose these leaders as the arsonists whose poor project management practices are
what started the fires.
Monday, March 21, 2016
21st Century Project Management
21st century project management
is fundamentally different from 20th century project
management. Yes, there are still start
and end dates, activities and deliverables, and budgets and project teams. But the management of those project attributes
is different. And if you don’t
understand those differences, your projects will struggle in the 21st
century business environment.
Project Management Has Been Around for Ages
Now to be clear, project management has
been around for thousands of years. The
pyramids in Egypt, the Roman aqueducts, and the Great Wall of China all had
project managers who planned and organized the work. They may not have had the title “Project
Manager,” but someone was in charge. As
far as we know, none of them held the PMP credential. Since Henry Gantt did not introduce the Gantt
Chart until the beginning of the 20th century, that was not
available to them. And we are certain
that none of them used either Microsoft Project or Primavera. Nevertheless, the projects were
successful.
So if projects were successful thousands of
years ago despite not having project managers with a PMP, Gantt Charts, or
project management software, we can conclude that project management is more
than just tools and certification.
There are components of the business and project environment that must also
be considered. So if the business
environment of the 21st century is markedly different from the 20th
century, it follows that project management must also adapt to the new reality.
Let’s start with a definition of project
management. I will cite the one used by
the Project Management Institute, “Project management is the application of knowledge,
skills, tools, and techniques to project activities to meet the project
requirements.” This definition
illustrates the point that was just made.
Project management relies on knowledge, skills, tools and techniques. If these change in the business environment,
the project management practices should also change.
Early 20th Century
Let’s consider some of the ways that the 21st
century business environment is different from the 20th century business
environment. At the beginning of the 20th
century, Fredrick Winslow Taylor and scientific management was all the
rage. This meant that activities were
planned in detail and standardized. Everything
was planned and tracked. Performance
targets were set and measurements were seen as the key to good management.
This was a perfect environment for the
introduction of the Gantt Chart and Work Breakdown Structure (WBS) to plan and
control project activities.
Organizations were hierarchical and functions operated in separate “silos”
that were managed for functional excellence.
Techniques like Critical Path were introduced to analyze and optimize
project schedules. Other techniques
like Earned Value Management came along and provided strict accountability for
cost and schedule on every aspect of the project. Project management was now part of scientific
management and all managers were expected to be able to use these techniques
Late 20th Century
In the latter part of the 20th
century business was transformed by computers and revolutionary changes in
communication and transportation technology.
These advances in science led to changes in how business systems
operated. Computers dramatically improved the
performance of almost all products, processes and systems. Communication and transportation changes resulted
in almost all industries becoming global and operating 24/7. With respect to projects, the speed of change
and the decentralization of project teams compounded the effects of project
complexity and urgency. To address these
issues, companies turned to project management certification and new project
management tools and techniques that managed complexity.
At the end of the 20th century,
project management had reached a new level of professionalism. It was now a recognized management discipline
and career field. Project managers had to
manage complexity in a fast changing environment. They were often required to operate both
strategically and tactically. Sophisticated
project management software applications were used on large and small projects.
In addition, an entire industry had sprung
up around project management. Many project
management consultancies, training programs, books, journals, magazines, and
certification programs abounded.
Researchers were analyzing projects to identify best practices and
project management gurus were out on speaking tours. Not to mention the numerous project
management software applications which were on the market. Project management was no longer an
additional duty of operational managers; it was now a stand-alone management discipline.
21st Century
We are now well into the 21st
century and we can see further business transformation. Big data and the internet of things is
transforming business again. In the 20th
century it was impossible for a manager of a global business operation, or even
a global project, to have all information about all activities instantly
available. Therefore, management
disciplines focused on how to discern business performance and issues from
summary information or how to infer it from a narrow slice of actual real-time
data. But that is all changing.
Companies can now get real-time data about
all business processes, including what is happening at customers or suppliers,
and make that information immediately available to managers. Computers can be constantly sifting the data
looking for special conditions or patterns that the managers specify. And decision and actions can be implemented
faster than most people can keep up with.
The role of the manager is changing.
The manager must now spend their time engaging with customers,
suppliers, and employees to ensure alignment of activities and interests. The arts of negotiation, motivation, conflict
resolution and empowerment are the hallmarks of good management, not directing,
controlling, and analyzing.
This is especially true for project
managers. The project management tools
and systems can now do all of the analytical side of project management. However, the diverse and decentralized project
teams need a project manager who is focused on the team alignment and
integration. The project manager must
build a relationship with team members to ensure they are appropriately
engaged.
For those of us who started project
management using the methods of the early 20th century (which in
many cases were still the standard until the 1980’s) and have gone through the
transition to the methods of the late 20th century, the thought of another
transformation is daunting. But that is
the reality of our today’s business environment. Will we still have certifications and project
management software applications – of course.
But those will just be tools in the tool box, not a measure of project
management acumen. Project managers will
be totally connected with technology –
but the technology will not be what is managed, rather the technology will be
the enabler for the project manager to work with stakeholders and team
members. The more technically advanced
we become, the more important the inter-personal relationships become.
So the new 21st century project
manager is first and foremost a “people person.” They are great communicators and
motivators. Yes, they are technically
savvy with respect to the use of project management software and communication
technology. But these are just tools,
the discipline of project management is now resource alignment and empowered
engagement across functional and organizational lines.
Monday, March 7, 2016
Proactive & Reactive Risk Management
I was recently working with a company who didn’t
understand the difference between proactive and reactive risk management on
product development projects. Oh sure,
they could explain the concept in a meeting, but their business practices told
a different story.
First, let’s acknowledge that we need
both. Proactive risk management can
avoid and minimize risks. But sometimes
the unexpected happens and we need to respond to it when it does. A strong risk management approach will
periodically assess the project to identify risks and proactively take actions
to avoid and mitigate negative risks while enhancing and leveraging positive
risks. And at the same time, the risk
management approach will be constantly assessing progress and variances – both technical
and project progress – to determine when unexpected conditions have occurred. An analysis of those conditions will lead to
appropriate corrective actions or responses.
Risk Events
Let’s look at the attributes of proactive
and reactive risk management, at least as they apply to technology or product
development project. Risk is defined by
the Project Management Institute as, “An uncertain event or condition that, if
it occurs, has a positive or negative effect on one or more project objectives.” There are three aspects I want to
highlight. First it is an uncertain
event. Second it can be both positive
and negative. And third, it effects on
or more project objectives.
Proactive risk management focuses on
identifying the uncertain events and estimating the effects of the
objectives. Reactive risk management
starts with the unexpected effects and attempts to determine the events that
caused those effects. In both cases,
actions are taken to protect the project goals.
However, in proactive risk management, an action is taken to avoid or
prevent a negative effect or to enable or enhance a positive effect. In contrast, with reactive risk management an
action is taken to recover or compensate for the already existing unexpected negative
effect on the goal or an action is taken to lock in the benefits from an
already existing unexpected positive effect on the goal.
Effective risk management needs to include
both proactive and reactive elements. It is obvious that if you don’t do
either, disaster is likely to strike your project. But even if you do one, but not the other,
disaster is still likely to strike. Let
me illustrate using the experiences of the company I mentioned earlier.
Proactive without Reactive Risk Management
This company did proactive risk management
for project risk events. They conducted
a risk analysis shortly after the project started where they considered a
variety of project risk events that could affect the project. These included schedule issues, resource
issues, and some technical issues. The
risk analysis was captured in a risk register, proactive risk responses were
identified and most were implemented.
And that was the last time that project risk was discussed on the
project until the accumulating disasters caused the project to be cancelled two
years later.
Proactive risk management was done and the
actions taken were good ones. But the company
and project team did not regularly assess project performance with respect to
cost and schedule goals. They just kept
changing the schedule and throwing resources at problems. There
were ample signs that other unexpected events had occurred and that the project
plan and project approach was not working.
However, the project team did not stop to assess what was going on and analyse
the project to determine the root cause or causes of the risk events. Therefore they never took appropriate
corrective actions. Finally two years
into the project, they were approximately 18 months behind to the original
schedule and the spending was nearly double the original budget.
Reactive without Proactive Risk Management
While the company did proactive risk
management with respect to project goals, they did not do any proactive risk
management with respect to technical goals.
This was a development project using emerging technology and it was
pushing that technology to an order of magnitude improvement in several of the
key technical performance characteristics.
In addition, the product was evolving from a complex mechanical product
to a system involving complex mechanical elements, electronics, software, and systems
integration with other customer systems.
The project team did not do any proactive technical risk
assessment. In fact technical risk was
never discussed in their project reviews – just technical problems.
The technical problems were addressed using
a reasonable and effective reactive risk management approach. As a problem was identified, a root cause
analysis was performed and a solution was created to solve that problem. But since no proactive risk management was
done, the solutions often then created even more technical problems. And when a technical problem was finally
solved, it would just unmask the next technical problem. The project went through a continuous set of
technical problems and issues, with the result that despite dozens of systems
being constructed, none of them was ever fully compliant with the specifications. Finally, after two years of work, the design
team reported to management that the current design approach was not robust
enough to ever meet the customer’s use requirements. If the
company wanted a product that would be satisfactory to the customer, they would
need to restart the development project with an entirely new concept.
Combining Proactive and Reactive
Risk Management
If the company had effectively combined
both proactive and reactive risk management approaches around either the
project or technical goals, the situation would have been recognized much sooner
and the project could have been salvaged.
The proactive project risk management made some good project
enhancements. If it had continued to
monitor for risk, it would have identified that something wasn’t right with the
technical approach and corrective actions could have been taken. The reactive technical risk management
continually fixed one problem after another, but a proactive analysis would
have identified that the fundamental concept was too risky and a different
approach would have been used.
The lesson for project managers is to do
proactive risk management early in the project.
And then monitor performance, identify variances and do effective root
cause analysis as the project progresses.
These complementary approaches should lead to project success.
Monday, February 1, 2016
Project Management Made Easy
Project management software has not made
this any easier. Many of the project
management software applications tout how intuitive and simple they are. But the reality is that they have automated
some of the more difficult and obscure aspects of project management. In order to really use the software, you
already need to be adept at project management.
So for most people, the software either becomes a glorified chart-making
tool or it is used as barriers to keep the “unwashed masses” out of the intricate
mysteries of professional project management.
But in a nutshell, project management is
just organizing who does what and when they do it so as to achieve a goal or
objective. When the work is very
difficult, or there are many people, or there are some tight constraints around
the objective; then the project management disciplines can help to identify and
overcome unique issues. But it still
comes down to “who,” “what,” and “when” to achieve the goal.
That is why I find that most of the time
when I am working with an organization that is trying to embrace project
management; I need to focus on how to keep things simple. What I have found is that there are two very
simple approaches to organizing the “who,” “what” and “when” that everyone can
understand and work with.
Post-It Note Project Management
The first is to use “Post-it” notes and a
storyboard. In this case, every activity
is listed on its own “Post-it” note. I
then add the name or names of who will do the activity and the start or end
date.
The “Post-It” notes are organized
on the storyboard in whatever way makes the most sense to the team. I have organized them in columns where each
column represents a week or each column represents an individual on the
team. I have also organized them by
grouping the tasks for a deliverable around each other in more of a
mind-mapping approach.
The great things about this approach are
that it is quick, easy to understand, visual, and easy to maintain the
status. The way I manage status is that whenever
a project activity is complete, I move the “Post-It” note to the lower right
hand corner of the storyboard. So it is
easy to track what work is left to be done.
If another required activity is discovered, just add the “Post-it”
note. Updates and changes are easy to
track.
There are several limitations
with this approach. First, you need a
co-located team so that everyone can see and track the storyboard. Also, I have found that if there are too many
activities it is difficult to fit them all on the storyboard and track progress. My rule of thumb is that this approach is
limited to 100 activities or less.
Finally, if there are many linkages between activities throughout the project,
this approach does not capture that well and another tool or analysis is needed
to track those linkages. With that said,
most of the organizations that have small ad hoc teams for conducting part-time
projects can use this approach.
Spreadsheet Project Management
The next approach is to use a spreadsheet
for planning and tracking the project activities. Now I am not talking about using the advanced
math functions of the spreadsheet, rather I am using it as a poor man’s
database. The reason I like to use a
spreadsheet is because all most all mobile devices, laptops, tablets, and phones
have a spreadsheet application. If I put
the project plan and status in a simple spreadsheet, I can share it with a distributed
team and update it any time and from anywhere.
I set up my spreadsheet so that each row is
a project task or activity and each column represents information about that
task or activity. So one column is the
task, another column is the task completion criteria – or “definition of done” –
for that task. I also have a column for
who is doing the work, the start date, end date, notes or comments, and current
status. Another thing I like to do with
the spreadsheet is change the
color of the row based upon status. That way activities that are done are late or
in work can pop out when your check the spreadsheet.
There are several advantages of this
approach. It can be easily shared with team members that
are not co-located. You can easily add
hundreds of tasks (I have used it on projects with over 400 tasks and
activities). It is easy to sort the
activities by date, by status or by who is doing the work. And as I mentioned it is portable.
There are several disadvantages. One is that you can only see a few rows at a
time on your screen. Another is one that
was mentioned with the Post-it notes; that is that it is difficult to track
linkages between the tasks and activities.
When you have the complex
linkages you should switch to a powerful project management software
application. And you probably need a
professional project manager then because of the complexity and risk.
So keep it simple. Use Post-it notes or spreadsheets where
possible. If you want to know more
about using either of these approaches, check out my online course on the
topic.
Tuesday, January 12, 2016
Powerball Project Management
This sounds a lot like what is happening in
the Powerball lottery. As the payout
keeps growing (it is now estimated to be $1.3 billion dollars), I see more and
more people spending money they can ill afford to spend on lottery tickets. They then cross their fingers and hope they
win; just like this project team kept hoping that one of the ideas they tried
might work.
Risk and Reward
Ask any financial adviser and they will
demonstrate that an individual will be far better off financially if they took
the average amount of money the typical Americans spends each year on lottery
tickets and invested that in a sound investment. Yes, someone does eventually win the lottery
and they receive a huge payout, but the vast majority of people who buy tickets
are losers and the money is wasted.
Even many of the people now buying a
lottery ticket will tell you that it is a stupid waste of money. But they are doing it anyway because the payout
has become so big. The risk is the same –
you are virtually guaranteed to lose your money. But the reward has grown to the point where
people are now willing to take the risk.
The reason the reward has grown is because there
have been no recent winners. The longer
the Powerball lottery goes without a winner, the larger the payout. It was somewhat similar on the innovation
project. None of the earlier ideas had
been feasible. An idea that gave
adequate product performance was too big, or not serviceable. An idea that was the right size, couldn’t
meet the specifications. It was like
having some of the winning numbers on the lottery ticket but not all of
them. The longer the project went
without a viable solution, the more management focused on the project. Whoever came up with the idea that would work
would be big hero in the company and be well compensated for their idea.
So ideas kept coming. In fact, the project team was growing. People were working overtime. There was a frenzy of activity – most of it
wasted effort. The project manager had
no control over what was happening.
Configuration control of product designs was lost. Testing was analysis was ad hoc and
unfocused. Different sub-teams
responsible for different components were using incompatible approaches for
subsystems that had to integrate with each other. The project manager could no longer even
report on project status because he had no idea what many of the people were
doing.
Discipline of Project Management
The company had lost sight of the
discipline of project management. Just
like disciplined investment of money will yield steady predictable growth in
the value of a portfolio, disciplined project management will yield steady
progress on a project. Starting with a
plan and doing regular risk reassessment and pulsing of the project will
identify the problems and issues. A
disciplined problem solving approach will lead to an understanding of the
nature of the problems and point to a solution strategy. Planning the solution and implementing the
solution plan keeps the project on track and moving to a successful conclusion.
Granted this isn’t the adrenaline rush of a
“Eureka” moment when using disciplined project management on an innovation
project. Nor does it lead to the discovery
of “heroes” in the business that suddenly emerge by creating the next
mega-million jackpot product line. But
it will prevent the business from wasting tons of money on worthless ideas. It
does provide a predictable approach to innovation and it keeps the project
manager and senior management informed and involved.
Incidentally, which project disciplined project
management approach you use is not critical.
What is most important is that you pick one and use it on your
project. Just like there are many
financial strategies, there are many innovation project management
methodologies. You might prefer
stage-gate over Agile. You may be a fan
of the PMBOK Guide®, or you may be an advocate of PRINCE2. You may be able to use an industry specific
methodology like APQP or IPPD. You may
prefer the rigor of Design for Six Sigma or the framework of the SDLC. Pick the one that best fits you industry and
culture – then actually use it.
Disciplined project management does not
mean nonsensical bureaucracy. It does
mean that you have a plan which is followed and updated periodically. It does mean that you do regular risk
assessment and variance analysis in order to make tweak the plan. It does mean that you have regular status
updates within the team and stakeholders to maintain alignment and
integration. These same principles apply
to wise financial investing.
Powerball project management is a recipe
for disaster. Chasing ideas with no project
plan, throwing resources at problems with no structured problem solving approach,
and getting caught up in the frenzy of the moment won’t bring you success. Keep in mind, the odds of winning the
Powerball jackpot is 1 in 292 million.
The odds of Powerball project management leading to a successful
innovation are about the same.
Monday, January 4, 2016
The Logical Flaw with Project Management
One of the reasons that companies struggle
with project management is that the approach they use has some basic logical
flaws. A company thinks it has some good project managers, and is disappointed when the results are poor. So the entire discipline of project management
gets a bad name in that company. But the
problem was not with using project management. The problem was that the logic behind their project management approach was flawed.
This is the logic often used in appointing project managers:
Major Premise: The best project managers
create project plans.
Minor Premise: Bob created a project plan.
Conclusion: Therefore, Bob is one of the
best project managers.
But then Bob’s project becomes a train
wreck and Bob and the project team are clueless as to why that happened or what
should be done. The problem was in the approach to project management. Let’s go back to the
major premise that was used.
The best project managers create project plans. There are several flaws in this logic. First, although it is true that the “best
project managers” create project plans, there is no statement about what the “worst
project managers” do. In fact, many of
the worst project managers also create project plans. And some of those project plans use all of
the latest forms, templates, software and are full of excruciating detail.
Second, the “best project managers” do much
more than just create project plans. They
execute their project plans. They
regularly do status checks and risk reviews.
They manage the stakeholder interactions and project teams wisely and
well. It is an ongoing continuous set of
interactions that are not part of planning – but are necessary for success.
Project Plans
Project plans come in all levels of
accuracy and completeness. Project plans
that are based upon incorrect assumptions about resource availability,
technical capability, or stakeholder interactions are doomed from the
start. I have seen many books and
courses on how to do project planning.
They often gloss over some of these points and instead focus on things
like the format of the WBS or critical path calculations. If the underlying assumptions about the
project conditions are wrong, everything else in the plan is just a fantasy.
Project management gurus often talk about
the need for upfront planning in a project.
The focus of that effort should not be just the technical planning
activities; it should be identifying and testing the assumptions and
constraints. There are assumptions about
business conditions and assumptions about project objectives. There are constraints on resources and
constraints on project options. If any
of these are missed, it can destroy the validity of the best formatted and
calculated project plan.
Unfortunately, there isn’t a simple (or even
complex) equation that can be applied to identify and test the assumptions and
constraints. Rather, the project manager
must meet with the stakeholders and ask probing questions about goals and
risks. They need to determine how much
support the stakeholders will really provide to the project – it is just
cheering on from the side lines, or will they dedicate time and money. The project manager needs to determine
realistic resource capability and capacity, regardless of what is
promised. These activities require
cross-functional and multi-level communication skills. It is one of the hardest things to teach
technical professionals. One of the most
challenging aspects of this activity is that you don’t know if you did it well until the project is over – which may be months or years later.
Project Execution
A project plan is a necessary condition,
but not a sufficient condition for excellent project management. The plan must still be executed – or at least
a variation on the plan must be executed.
Inevitably, something unexpected happens. The project manager must be regularly pulsing
the project to recognize the change and make the appropriate adjustment. A project manager who blindly follows a project
plan, even after a risk or issue has invalidated elements of the plan, can lead
the project into disaster.
In addition to regular updates and
adjustments to the plan, the project manager must interact with stakeholders
and team members to ensure appropriate decisions and actions. In many cases the project team members are
matrixed onto the project team. They
still have other responsibilities, often simultaneously working on multiple
projects. The project manager must keep
them engaged and focused. This usually
requires strong interpersonal skills and negotiating skills.
The stakeholders who are involved in project
decisions can delay and derail a project if they are not engaged regularly and
kept informed of the project status and project risks. Stakeholders often change during a
project. The project manager must bring
the new stakeholders up to speed. The
stakeholders often are looking at the “big picture” in the business and the project
manager is often focused on “immediate details.” If the project manager is not careful, the project
communication will actually confuse and irritate the stakeholders. A good project manager is able to switch
between the perspectives and effectively communicate and manage both “big
picture” and “immediate details.”
The Real Logic of Project Management
So let’s review. An organization that only focuses project managers
on creating complete and intricate project plans will likely be disappointed in
the actual project performance. A good project
plan is needed, but the most important aspect of planning is to understand and account
for the assumptions and constraints – not just filling out forms and
spreadsheets. Then once the plan is in
place, the project manager must stay flexible to modify the plan when
appropriate. And the plan is not
enough; the project manager must engage the stakeholders and team members to
keep things running smoothly and achieve project success.
This leads us to a new logical statement:
Major Premise 1: The best project managers
create project plans based upon realistic project assumptions and constraints.
Major Premise 2: The best project managers
adapt their plans throughout the project to reflect changing conditions.
Major Premise 3: The best project managers interact with
stakeholders and team members regularly to ensure alignment and appropriate
actions and decisions.
Minor Premise: Jill creates project plans
that are based upon realistic assumptions and constraints; she modifies them to
reflect changing conditions; and she regularly interacts with stakeholders and
team members to ensure alignment and appropriate actions and decisions.
Conclusion: Jill is one of the best project managers.
Monday, December 21, 2015
The Problem with RACI
While the Project Management Body of
Knowledge (PMBOK Guide®) may refer to it as a Responsibility Accountability
Matrix, everyone I know calls it a RACI Matrix. It is supposed to clarify roles
and responsibilities, yet it often creates more confusion that it clarifies. So let’s look at this tool, the benefits and the
pitfalls that create the problems.
Assigning responsibility for work is an
age-old principle. Even in early
civilization, some people were designated to have certain responsibilities. The
ancient kings had cupbearer, chariot drivers, shield-bearers, and ministers of
all types. These individuals had specific
responsibilities and if they didn’t perform the punishment was often sharp and
swift. In more modern times, thanks to
Fredrick Winslow Taylor and scientific management theory, everyone in business
has a designated role or position and they are expected to become expert at the
responsibilities associated with that role.
But projects are a little different. They don’t always lend themselves to
scientific management principles. Projects are temporary endeavours undertaken
to create a unique result. Individuals
on the project team are temporarily assigned to work on project activities, and
some of those activities may not be well defined. Because of the unique nature of projects, a
pattern may not already exist. Roles, responsibilities,
authority, and accountability need to be assigned to prevent duplication or
work or missing work. Which brings us to
the RACI matrix.
RACI Matrix
The RACI matrix is the most common tool for
assigning roles and responsibility to project team members. The matrix is structured by placing the
project tasks on one side of the matrix, normally the vertical axis; and the project
team members on the other side of the matrix, normally the horizontal axis. The role of each individual with respect to
each task is then noted in the matrix as either R – Responsible, A –
Accountable, C – Consulted, I –Informed, or left blank if the individual has no
role.
The RACI matrix assigns a role to each
individual, but it does not clarify what they are supposed to do. And that is what leads to the confusion. Who plans the task – the “Accountable” person
or the “Responsible” person? I have seen
it explained both ways. Does the “Consulted”
person only participate when asked, or are they expected to engage and ensure
their perspective is included? Again I
have heard it described both ways. And
then there is the question, “How can someone be accountable but not
responsible, or responsible but not accountable?”
Questions like these and others have led to
a plethora of variations on the RACI matrix.
The fact that there are so many variations is an indication that there
is a major flaw with the RACI approach.
If it was working well, people wouldn’t be trying so hard to improve it. Let me
list a few of the alternate approaches.
Alternate Responsibility Matrix Approaches
- ARCI – rearranging the letters because Accountable is more important than Responsible.
- RASI – Responsible, Accountable, Support, and Informed attempts to better define the original Consult role by now calling it Support.
- RACIQ – Responsible, Accountable, Consulted, Informed, Quality reviewer – this adds a role for review and approval.
- RACIO – Responsible, Accountable, Consulted, Informed, Omitted – this approach is meant to ensure that some individuals do not engage on a task and tamper with what is happening.
- RATSI – Responsibility, Authority, Task, Support, Informed – a slightly different segmentation of roles meant to clarify the differences as compared to the original RACI.
- RAPID – Recommend, Agree, Perform, Input, Decide – a variation that focuses on decision making authority rather than on the actual task activity.
- PACSI – Perform, Accountable, Control, Support and Informed – a variation that identifies some activities that must be done in addition to roles.
- DACI – Drivers, Approvers, Contributors, Informed – a variation that focuses on the type of activity that the person does rather than their role.
- CLAM – Contributes, Leads, Approves, Monitors – another variation that focuses on the type of activity rather than roles.
There are probably more, these are just the
ones that I am aware of.
The Problem
So what is the fundamental problem with RACI? I believe it is that while defining roles, it
does not clarify actions. But clear
actions are what a project needs. As a retrospective
tool to look back on a situation, RACI is effective. It can determine who was responsible for success
or failure? Who was accountable for ensuring
the task was completed? Who was
consulted along the way and how effective was their input? And who was or was not informed and what
impact did that have on the project?
Great questions when doing a post-mortem on a project; but not very
helpful for proactive project management.
When
planning and executing a project, the project team members need to know who is
doing what. A matrix focused on actions
associated with each task is much more beneficial to the team. Who is planning the work? Who will be helping on the task? Who are the stakeholders that have to approve
or sign off on the results of the task?
With these answers, the project leader and project team can manage their
resources, coordinate the schedule, and ensure that risk mitigation plans are
being executed in a proactive manner.
They don’t have to wait for success or failure and they try to
understand what happened.
Recommendation: DACI or CLAM
For that reason, I recommend the use of
either the DACI or CLAM approach. These
are activity-based matrices. I have found
that the level of confusion concerning who is doing what is significantly
reduced when these are used in project planning and execution.
Monday, December 14, 2015
VUCA Product Development
In most companies, developing new products
is a critical component of strategy.
Many companies are finding this to be more and more difficult as their environment increases in VUCA. The acronym
VUCA stands for Volatility, Uncertainty, Complexity, and Ambiguity. This acronym was created and gained
recognition in the strategic planning circles of the US military during the
past 15 years. A body of knowledge is
being developed around leadership in the VUCA world, with numerous articles and
books published in the past few years.
Bob Johansen has proposed a leadership
response to the VUCA environment which he titles VUCA Prime. According to Johansen, volatility is
countered by vision, uncertainty is countered by understanding, complexity is
countered by clarity, and ambiguity is countered by agility. Let’s take a look
at each of the elements of VUCA and VUCA Prime as they apply to product
development.
Volatility
Volatile is defined as changeable – and often
with an explosive or fleeting connotation.
Volatile situations are full of surprises. Vision is the recommended leadership response. Developing and articulating a clear vision
will assist an organization through the volatility be reducing the disorientation
that occurs when a volatile situation unfolds.
Even though there is rapid changes happening all around, the vision and
direction stay constant; providing a basis for decision-making and action.
Product development involving innovative new
technology, or a marketplace that is fast developing with new customers and
competitors, can often be volatile. The
vision that is needed for the product development team is a clear product line
strategy. The strategy that has
identified target markets and the characteristics of new products will guide
the product development team through the technology, design, and business trade-offs
that must be made when volatility strikes.
Without a clear product line strategy, the product development team
often stalls as they start chasing options and waiting for decisions from
stakeholders.
Uncertainty
Uncertain is defined as the state of being
unpredictable and indeterminate. There
are numerous significant unknowns in the business situation. The environment is novel to the point that
past experience cannot be used as the measure for what should be done now. However, in an uncertain environment, there
are facts that could be discovered. The recommended response to uncertainty is
understanding. This requires
investigation, fact-finding, and analysis.
Rather than responding in a dogmatic manner using outdated principles,
the response is to slow down and learn what is actually happening.
Within the product development environment
for innovative new products; there is normally uncertainty with respect to
customer needs, product performance, and market response. There are two approaches being used to create
understanding within product development methodologies. One approach is to do extensive upfront analysis
using tools such as the Quality Function Deployment. The other approach is to create a series of
rapid prototypes of a minimally viable product to get “real-world” experience
and feedback. I have used both
approaches and there are pros and cons for each. The key takeaway for this discussion is that there
is work that must be done to gain understanding. And that work needs to be built into the
development project plan.
Complexity
Complex is defined as intricate, often
complicated, interconnected parts, processes, or organizations. With complexity comes options and
opportunities. Some of these options and
opportunities are very favourable and some are disastrous. Navigating through the complexity requires
numerous decisions. The recommended response
to complexity is clarity. Clarity exposes
the decision points and the options.
Clarity will also often provide a framework for understanding the
implications of decisions. Clarity
exposes pathways through the complexity.
Product development of new innovative
products will often involve complexity on several levels. If the product is a system, there will be
multiple components, possibly hardware and software, that must all work
together. And research shows that system
integration and test is one of the most likely areas of a product development project
to overrun both time and money. In
addition, there is often organizational complexity. Marketing is developing requirements,
engineering is creating designs, quality is establishing test and inspection
methodologies, operations is setting up manufacturing and logistics processes
and facilities, IT is bringing new databases online and possibly new systems
for support. All of these functions must
work together and a change in one cascades through all the rest. Establishing a stage-gate product development
methodology with defined practices and decisions points will go a long way to creating
clarity in product development.
Ambiguity
Ambiguous is defined as obscure, indistinct,
and with numerous possible interpretations.
Unlike our definition for uncertain where facts are available but are
not yet known; in an ambiguous environment there is normally no “right” or “wrong”
answer. Instead the answer is always, “it
depends.” The recommended response to
ambiguity is agility. This means that as
the fluid situation continues to change, the decisions are revised and updated
frequently. Nothing is ever final; it
is just the “current state,” with the expectation that change will soon be required.
In the global marketplace, industries are
separating into those that are ambiguous and those that are rigid. The highly regulated industries have a
tendency to be very rigid and those that are not regulated are often
ambiguous. But regardless of the
industry, the product development environment is ambiguous. It follows that an ambiguous end market will
create an ambiguous product development process. As the target for product definition and
performance is constantly changing, whatever product is developed will
immediately need an upgrade or replacement product. But even in rigid end markets, development
is ambiguous. The regulatory environment
is often different in different countries or areas, and these regulations are
frequently changing. In addition, the
regulatory agencies interpretations of regulations are often inconsistent. Regardless of the industry, a rapid pulsing
process is needed to determine the current state of the market and industry
environment. This must be coupled with a
robust change management process for product development. Finally,
the product development metrics must be focused on business success or failure
of the product, not on time and budget targets for the project.
If you are involved in product development
today, you are probably experiencing VUCA.
You may reminisce about the “good old days” when things were calm and
simple. But don’t expect those days to
return. Instead embrace an approach to
have vision, understanding, clarity and agility.
Monday, December 7, 2015
Learning Lessons from Lessons Learned
When I ask people why they haven’t done
one, I get many different reasons. “Everyone
is busy on other projects now.” ‘Why bother, we won’t change anything.” “Most
of the team at the end of the project is different from the beginning team. They didn’t participate in many of the
decisions.” In fact, often these are backwards looking,
blame-focused sessions. When that
occurs, it is an indicator that the organization and project teams don’t
understand how to use these sessions.
I would like to discuss five elements of
effective reviews. These are the
purpose, the timing, the participants, the questions asked, and the follow-up.
Purpose
The purpose of these sessions is continuous
improvement. These are not meant to be
final project reports or a history of what happened. They are intended to improve the planning and
execution of the current and future projects.
One of the implications of this purpose is that anything can be discussed. There are no “sacred cows.” Don’t avoid subjects because it many hurt
someone’s feelings or it makes them uncomfortable. The goal is to improve performance. If we ignore some aspect of performance, it
will not improve.
Timing
A mistake often made when doing project
reviews is that the review occurs long after the project is over and the review
then considers the entire project. A
much better approach is to do a quick review after each phase or milestone with
the project team so that they can immediately take action to improve the
remainder of the project. This type of
review doesn’t need to be an all-day offsite meeting with formal facilitators
and reports. It can be a pizza lunch
with post-it notes on a white board.
Let’s consider for a moment one of the best
models of how to conduct one of these sessions, and that is the US Army’s After
Action Review format. First, note that
it is not an “After War Review” with Monday morning quarterbacks looking back
over years of history and trying to find the big lessons of the war. It is a review that is immediately conducted
following an action or event. Everyone
from the team is still there. The events
are fresh in everyone’s mind, and because it is focused on what the team just
did; many of the recommendations are immediately actionable by the team.
Participants
This gets us to the participants in the
review. I recommend that it is the team,
the whole team, and nothing but the team.
Well, you may want to have someone from the PMO or another project
leader to help take notes and facilitate.
This is especially true if there were some leadership problems and the
team might be uncomfortable discussing this in a meeting being run by the
project leader. There is no need for
senior management in this meeting. Their
presence is likely to repress the conversation.
It is appropriate for the project leader to provide a summary of the
results to senior management and the PMO.
But the discussion is likely to be much more open and honest if the meeting
is just the team members.
Questions
The agenda for the meeting is very
simple. What is going right and what is
going wrong. The team may want to vent a
little if there are problems or celebrate if things are going well. Let them release a little emotion, but then
focus them on these questions:
- What is going well that we want to continue?
- What is not going well that we need to change?
- What should we do differently as part of the change?
- What recommendations do you want to make to the organization to pass onto other teams?
Follow-up
Well, as you can see from the questions, we
anticipate that we will want to make changes.
It is possible that the team may say that everything is going great and
nothing should change. When that is the
case, the team should be making a recommendation to the organization so other
teams can copy their result. However,
most of the time there will be some changes.
By conducting the review with the current project team, they can also
decide what they will change – starting tomorrow. I like to get very specific when I discuss
the changes. I go around the room and
ask each person what they personally will be doing differently. Doing this in the room among the team members
will improve personal accountability among the team members.
Turning these reviews into forward looking
change events instead of backward looking blame events will make them
productive. They really will drive
continuous improvement.
Monday, November 9, 2015
Project Kanban – Integrating Scope, Schedule, and Resources
This approach is often tied to Agile
methodologies, but it has actually been around far longer. I was using a modified Kanban project scheduling
tool in the 1980’s. The tool shows the
relationship between scope schedule and resources. Like the Gantt chart, it is very effective
for managing the day-to-day status and tracking. And also, like the Gantt chart, it is a tool
that can be used with many different project management methodologies.
This tool works best for those projects
where many different deliverables go through similar steps or activities. The Kanban schedule is set up as a
matrix. The vertical side of the matrix
is the list of project deliverables. The
horizontal side is the steps or activities in the project. Normally, at the top of the matrix, the level
of resources available for each step is listed either in terms of the number of
individuals or the number of deliverables that can be actively worked at one
time. See the diagram below.
Kanban Principles
Kanban scheduling relies on two important
principles. The first is that it is “pull”
scheduling, not “push” scheduling. This
means that a deliverable does not move to the next step until there is a
resource available to work on it. As soon
as the resource completes a deliverable, it pulls the next deliverable from the
preceding step. That way a step does not
become glutted with many deliverables all hung up at a bottleneck.
The second principle is that it is a “visual”
scheduling tool. The “pull” indicator is
visual and the status of how many items being worked on at one time is also
visual on the matrix. In addition, I
normally will change the cell color of the deliverable and the step to show
what is being worked on and what is completed.
Visual control normally leads to
improved project team communication because it is simple to understand.
Kanban Weaknesses
There are two weaknesses with using Kanban
scheduling. The first is that it is
difficult to translate the schedule to a calendar. The Kanban schedule is a matrix. Often the matrix will have dates for each
step of each deliverable, but it is difficult to take a table of dates and
picture what is happening on a calendar.
That is why I normally will also use a calendar-based Milestone chart
when using a Kanban schedule.
The second weakness is that it is very
difficult to track inter-relationships between deliverables. If the deliverables are separable that is
not a problem. If there are numerous
points of interaction between deliverables, the ability to pull can be
confused. In that case, the network
diagram is a better scheduling tool because it shows those relationships and
allows the project team to calculate a critical path.
Planning
with Kanban
So let’s talk through how a project plan
would be represented using a Kanban schedule.
First create the list of deliverables – this is usually derived from the
scope statement or project contract.
Then determine the categories of activities that must be accomplished on
each of the deliverables. This is the
same type of activity you would do when developing a work breakdown
structure. With these two pieces you can
build the matrix. Next, determine the
resources capacity you have for each activity type. Finally, estimate the amount of time required
for each deliverable and estimate the dates when each activity will end for
each deliverable. Place that date in the
appropriate cell of the matrix. See the
diagram below.
Managing Project Progress with Kanban
The Kanban tool is an excellent tool for managing
day-to-day project activities. Thanks to
the visual control aspect, it is easy to see what is underway, what is
complete, and what is coming up next. Because
I use cell colors to indicate activity status, the current project status is
easy to see. Also, problem deliverables
or problem steps will quickly “jump out” from a review of the matrix.
In the diagram below it, the present date
is July 25. It is easy to see that
Deliverable #7 is behind schedule. This
is a major issue on the project and should be receiving the project manager’s
focused attention. In addition, the “Update/Debug”
step is becoming a bottleneck. There are
five deliverables that could in process at that step, #3, #4, #6, #10, and
#11. However, the capacity is only to
work on three, so deliverables #4 and #11 are not being worked on by anyone at
this time. So far it is not a major
bottleneck, but deliverables #2, #8, #12, and #13 are in work in the previous
activity and could be turned over to the update/debug queue soon.
The Kanban schedule tool can be very useful
for some types of projects. It combines
scope, schedule and resources into one easy to read visual display. If this tool is not currently in your project
management toolbox, you should consider adding it.
Monday, November 2, 2015
Channels, Navigational Beacons, and Project Management
When bringing a large ship up a river into
a harbor, the captain and pilot must be careful that they don’t run
aground. There is a channel of deep
water that they must follow. By staying
in the channel they avoid hazards such as rocks, reefs and sand bars. There are often navigational beacons and
buoys marking the channel to assist the captain and pilot. If there are no navigational beacons, the
captain must find a local experienced pilot, or proceed very slowly, taking
soundings all along the way. The local
experienced pilot can still bring the ship safely into harbor because he or
she knows the path of the channel and can tell where the safe path is by other
landmarks. The slow approach and
soundings will tell the captain of dangers and allow the ship to maneuver to
avoid them.
You are probably thinking, “What does this
have to do with project management?”
Well, channels and navigational beacons are great metaphors for some
important project management principles.
Every project is different, yet every
project has some similarities. Each project
has a start and an end point. There is
an optimal path the project should follow for achieving the lowest cost or
fastest time. Depending upon the company
and the project type, that path is unique.
Often when starting off on the project “voyage,” the water looks calm
and smooth, but there are reefs, shoals, and shallow water that can cause the
project to run aground. The project manager,
just like a captain or ship’s pilot, must navigate through the hazards and
bring the project safely to its end point.
To assist the project manager, many times
an organization will create a project management methodology with templates,
checklists, and reviews that are used to “chart” the path the project should
follow. The methodology defines a
channel that has been determined to be the best path to navigate the risks and
dangers of the project. The reviews,
checklists and templates are the navigational beacons and buoys that are used
by the project managers to guide them through the channel. The channel is still likely to have some
sharp turns and dangerous eddies, but the templates, checklists, and reviews
are there to guide the project manager through these dangers.
Without pushing the metaphor too far, we
can see some of the problems and challenges that project managers and organizations
face by considering some of the challenges associated with channels and
navigational aids.
- One problem is that the channel will often change over time. Storms can shift sand bars and a channel can quickly be blocked. In fact there may not be a navigable channel following a storm. Within companies, re-organizations or new initiatives and systems can change how work is done. The original channel may no longer exist and a new channel must be found or dredged.
- Another problem is that the channel fills up with mud and sand over time so that it is no longer deep enough for the ships to come in. When that occurs, the channel must be dredged to clean it out. Within a company, a project management methodology often becomes cluttered over time. A Lesson Learned on one project adds a new checklist or template. The new checklist is added, but the old ineffective checklist is not removed. A new management team wants to do project reviews in a different manner than before. The new reviews are added, but the old reviews are not removed. The organization needs to periodically review the “channel” in the project management methodology to ensure that it does not get cluttered up with unneeded or ineffective templates, checklists and reviews.
- A third problem is the use of the beacons. Small boats can often scoot around the beacons and maneuver outside the channel because they have a very shallow draft. As the captains of those boats are promoted to larger ships with deeper drafts, they can no longer safely navigate outside the channel. Within companies, small projects can often be successful even though they did not use some of the templates, checklists and reviews because their scope or team is so small. However, when these project managers are promoted to the large projects, that same behavior can lead to disaster. The larger the project the more important it is to use the full project management methodology.
- A fourth problem is that the captain and pilot must be able to see the navigational aids and understand what they mean. This requires training. In a river or harbor, the color, shape, and number of the navigational aid has a distinct meaning. Within project management, checklists, templates and reviews also serve a distinct purpose. Using the wrong checklist at the wrong time in a project can lead to bad decisions that create project disasters. Project managers, project sponsors and key project team members need to learn the methodology. Project management methodology training, tools and technique training, and periodic performance reviews are needed to ensure that project managers are effectively working with the project management methodology.
Whether your project is best represented by
a super tanker, a catamaran yacht, or a two-person dingy, it is still important
to know the channel and to understand the navigational beacons. Using them appropriately will enable you to
bring your project safely into the harbor.
Subscribe to:
Comments (Atom)














