In many cases, tell a project manager they must use earned
value analysis on a project and you will hear a groan. Earned Value Management has been tainted with
an aura of overwhelming bureaucracy and incomprehensible numbers and
ratios. While some organizations may
have done their best to confuse and confound project managers and project teams
with Earned Value Management – it is really a very basic and easy to use set of
project analytics. This blog post will
explain the earned value variance analysis and other blog posts will discuss
project baselines, project forecasting, and the role of the cost Account Manager. Or get everything together in the ebook found at the end of this post.
Earned
Value Management
Earned
value management is an analytical approach for determining the current cost and
schedule status of a project and for forecasting the final cost of a
project. It combines scope, schedule and
resource management into one set of measurements. When used properly it will simplify and
reduce the effort needed to provide effective project management control.
Earned
Value Management is based upon the comparison of three different perspectives
on a project. The first perspective is
the project planned value (PV) which is the estimated cost of each activity time
phased according to the project schedule.
The next baseline is the earned value (EV) which is the estimated cost
of the project activities that have been completed. The final baseline is the actual cost (AC) which
is the amount of money spent completing the work that has been done on the
project. These baselines are discussed
in more detail in the blog post, “Demystifying Earned Value – the Baselines.”
Variance
Projects
hardly ever go exactly according to plan (at least I have never had one that
went exactly to plan). Some things go
better than expected, some go worse. Some tasks start early, some late, and
some are just different. Variance occurs when the actual situation is different
from the planned or expected situation.
In projects, variance analysis applies to schedule variance and cost
variance. Variance analysis helps the project team understand
why things are different than expected, and more importantly, what they should
do about it, if anything.
Variance is
always backward looking. It analyses what
has happened. (We will cover forecasting
in another blog.) We typically are concerned with two different time horizons
when determining project variance. One
is the variance since the start of the project, known as cumulative variance. This variance will be focused on trends. The second is the variance in the current
month or week. This is focused on recent
occurrences. Most earned value reports
will show both variances.
Cost
Variance
Cost
variance is the under-run or over-run of actual costs (AC) as compared to the
estimated project costs of the work that has been completed (EV). When evaluating project cost variance, it is
important to exclude the effect of tasks that are ahead or behind schedule,
which is why EV is used instead of PV.
The PV has embedded schedule assumptions for which tasks will occur in
which months. If a task is not worked on
during a month because of a schedule delay, that could appear to be an under-run
to the project for that month if we use PV.
However, if the task is accomplished the following month, it would
appear to be an over-run for that month since the cost occurred in that month
without any planned cost for that task occurring in that month. The Earned Value Management approach allows
us to eliminate the schedule impact on cost variance by using EV for the
baseline cost instead of PV. The EV
represents the planned or budgeted cost for the work that has actually been
performed. The AC is the total costs
associated with doing that work.
Cost
variance that is calculated using EV and AC from the beginning of the project
is the cumulative variance. It is an
excellent indication of trends and helps to predict what will likely continue
on the project unless changes are made. However, the amount of the cumulative cost
variance – either under-run or over-run – is typically unchangeable. Most of those tasks are completed and the
variance cannot be impacted. The current
period cost variance analysis will provide insight as to whether the tasks that
are currently underway are over-running or under-running. These are indications of immediate risks and
opportunities that the project manager should investigate.
The cost
variance is calculated as the difference between EV and AC. A positive cost variance is an under-run and a
negative cost variance is an over-run.
Cost
Variance = EV – AC
Current
period cost variance uses the EV and AC for the current month. Cumulative cost variance uses the EV and AC
since the project has started.
Schedule
Variance
Schedule
variance is the ahead of schedule or behind schedule position of the project as
compared to the schedule found in the project plan (PV). Normally project managers present schedule
variance in terms of time (days or weeks) ahead of or behind schedule. However, since all earned value analysis
baselines are expressed using money; the schedule variance in earned value
analysis is also denominated in money.
(Hey – time is money, right?)
The earned
value analysis schedule variance is the estimated cost of the work that has not
been done according to the project schedule plan. For work that is accomplished earlier than
scheduled, this would be a positive value representing the estimate of the work
accomplished early. For work that was
late this is a negative value representing the estimated cost of the work that
was not done when scheduled. The
schedule variance is then the difference between the EV, which is the estimated
or budgeted cost of the work that has been performed and the PV which is
estimated or budgeted cost of the work that should have been performed
according to the project plan.
The primary
concern for a project manager is negative schedule variance. This is cost that will need to occur at some
time on the project when those project activities finally occur. This becomes important near the end of a
fiscal year when the business is trying to plan the costs that will occur in
both the current year and the following year.
Keep your finance people informed if you have large earned value
schedule variances.
Schedule
Variance = EV – PV
Just as
with cost variance, this can be calculated both for the current month and for
the entire project since its start.
Hi Ray, Good article. It explains variances well. I had also written an article having all EVM Formulas and small definitions of each EVM term. It might be useful for your readers. Your article has complete explanation whereas mine is a summary of EVM.
ReplyDeleteBR
Praveen.