Monday, June 8, 2015

De-mystifying Earned Value – the Baselines

In many cases, tell a project manager they must use earned value analysis on a project and you will hear a groan.  Earned Value Management has been tainted with an aura of overwhelming bureaucracy and incomprehensible numbers and ratios.  While some organizations may have done their best to confuse and confound project managers and project teams with Earned Value Management – it is really a very basic and easy to use set of project analytics.  This blog post will explain the earned value baselines and future blog posts will discuss variance analysis, project forecasting, and the role of the cost account manager.  Or you can get everything in one document by ordering the ebook at the end of this post.

Earned Value Management

Earned value management is an analytical approach for determining the current cost and schedule status of a project and for forecasting the final cost of a project.  It combines scope, schedule and resource management into one set of measurements.  When used properly it will simplify and reduce the effort needed to provide effective project management control.

Earned Value Management is based upon the comparison of three different perspectives on a project.  The first perspective is the project plan – to include which tasks will be completed on which dates and how much they are estimated to cost.   Earned Value Management calls this the Planned Value (PV).  The second perspective is the current project schedule achievement – which is an assessment of which tasks are started; which tasks are completed; and the level of progress for those that are underway. Earned Value Management calls this the Earned Value (EV).  The third perspective is the current project spending – which is how much money has been spent on the project since it started.  Earned Value Management calls this the Actual Cost (AC).  The project manager should be managing all three of those perspectives regardless of whether Earned Value Management is being used.  

Earned Value Planning – Setting the PV

The PV is created using the Work Breakdown Structure (WBS), the project schedule, and the task estimates.  Every task in the WBS is assigned a separate account number in the financial system.  The cost estimate for every WBS task is then spread over the time periods (normally months) associated with the project schedule for that WBS task.  Those cost amounts are placed in the WBS account for the appropriate periods to create a time-phased task-level budget estimate.  This is the task PV.  Once all of the task PVs are complete, they can be summed into a project PV.

When spreading the task estimate across multiple time periods, one of two techniques is used.  The cost can be “level loaded.”  This means the costs are spread evenly across the time periods in which the task is scheduled to be accomplished.  The other approach to spreading the cost is “event loaded.”  In this case, the WBS task is planned at a micro-level (daily or weekly) and the cost associated with the work for each micro-time period is assigned to that period and then summed to the time periods used in the financial system (normally monthly). 

PV is expressed either as “Current PV” which is the PV that is planned for a particular month, or “Cumulative PV” which is the PV from the beginning of the project to the point in time under consideration (normally the current date). The final value of PV – that is the total PV for the project – is the Budget at Completion (BAC).

Setting Earned Value (EV)

Earned Value (EV) is a judgement call by the project manager and the project team concerning how much of a task has been completed.  The total possible earned value for a task is based upon the original budget estimate for that task, which is the task Planned Value (PV).  The percentage of a task that is completed is the percentage of value that has been “earned.”  If a task is 50% complete, the task has “earned” 50% of the planned value – regardless of the cost required to get to that point.  Before a task is started, its EV is 0 since none of the planned value has been earned yet.  When a task is complete, it has “earned” all of the value for that task, so the EV = PV.  EV for a task can never exceed the PV for a task, regardless of how much has been spent.  Nor can EV ever be negative.
A risk with earned value is that someone will claim that much of the value for a task has been earned, when in reality very little progress has been made.   To avoid this problem, many organizations adopt rules or practices for how earned value is to be credited.  This list is the most commonly used ones in my experience
  • Earned value amount is based upon the number of micro-tasks associated with a task that have been completed.  This requires detailed task planning at the micro-activity level.  This will be the most accurate, but it also takes the most work.  I normally use this approach for tasks that take longer than 2 months to complete.
  • 0-100: The earned value amount is zero until the task is complete, then the EV is 100%.of the PV.  This is easy to use and focuses team members on getting things done.  However, they are likely to start and do the easy tasks first and save the long and hard tasks for last.  It is best used with tasks of one week or less duration.
  • 30-70:  The earned value is set at 30% of the PV when the task starts and the additional 70% is credited when the task is completed.  This approach is easy to calculate.  It is not quite so harsh as the 0-100 approaches.  I normally use this for tasks that are longer than a week in duration but less than 2 months.


Determining Actual Cost (AC)

The AC element of Earned Value Management is the easiest for the project manager.  The business financial system collects costs.  As long as the project earned value cost accounts are created when the project PV baseline is set and the financial system can record costs by those account numbers, the AC will be automatically collected from the finance system.

With these three project perspectives, PV, EV, and AC, the project manager can determine the underlying causes of cost and schedule variances and forecast project completion.  These topics will be discussed in future blog posts.  If you would like to find out even more about earned value management, purchase this ebook.


1 comment:

  1. Hi Ray, Nicely explained. It is very important that an org. has a standard procedure for determining - like 0-100 or 30-70. Otherwise it causes lot of heartburn. Just to share my experience, I had written a introductory article on EVM. One of the reader on my blog said that EVM is totally impractical. I wrote another article just to explain practical utility of EVM.

    BR
    Praveen.

    ReplyDelete