Failure #1 - The Project Management Methodology Inhibits Project Action
In the summer of 1965, three years after the fires started, the federal Bureau of
Mines created a plan to address the fire.
This two phase plan would cost $2.5 million. The plan was approved, but
bureaucracy and red tape slowed things down so that Phase I did not start until
September of 1966. First project management failure by the federal government –
the project management methodology inhibits project action instead of enabling
it.
Failure #2 - Changing Scope To Fit The Budget; But Not Achieving The Project Goal
Phase I took longer and cost more than planned. When it was finally time to start Phase II,
in October of 1967, a re-estimate of Phase II indicated that the project would
now cost $4.5 million. Rather than spend
the money, the project was redefined.
The Phase I activities were expanded and the Phase II activities were
cancelled. This was done despite the report
issued in 1965 that said both phases were needed to control the fire. The expanded Phase I was completed. A project success clained, but the fie was still raging. Next project management failure – changing the
project scope to fit within the available budget and claim a “success,”
without considering the impact on the project goal.
Failure #3 - Refusing Help
By December of 1967 the fire had spread into an adjacent
coal field. The company that owned that
unmined coal was naturally quite concerned that the coal would be consumed
before they could dig it out. But
because the Bureau of Mines was involved in fighting the fire, the company was prohibited from doing any mining without Bureau approval. The
company offered to put the fire out at their own expense if they would be
allowed to dig out their coal. They even
offered to let the Bureau of Mines supervise the effort. However, the federal agency rejected the offer. Next project management failure – refusal to accept
help from others.
Abandoned house in Centralia, PA |
With the fire still burning and spreading, the Bureau of
Mines decided to try a new technique for building a barrier around the fire,
using fly ash. This innovative technique had worked
well in several tests. In May of 1969
this project was started in combination with yet another small excavation
trench. This effort was partially
effective in stopping the fire from spreading further towards downtown
Centralia, although the fire could continue to burn and spread in other directions, Therefore the project was of limited scope and did not completely surround
the fire and extinguish it. Although the fire was no longer spreading towards downton Cetnralia, by this time, three houses that were nearest
to the fire had already been condemned because they were full of carbon
monoxide venting from the fire. Next project
management failure – a partial success occurs and the team declares victory
without achieving the full project objective.
Failure #5 - Not Aligning Stakeholders Creates Delays And Confusion
Move forward now to 1976; periodic monitoring revealed that
the fly ash barrier constructed in 1969 had not sealed the fire. Hot gases, primarily poisonous carbon
monoxide, had jumped the barrier. Although it did not appear that the fire had
jumped the barrier, it was creeping around the edges of the trench. The Bureau of Mines
determined to conduct a repair project of the barrier and trench. Again bureaucratic red tape delayed the start
until July of 1977. Phase I repaired the
fly ash barrier and closed some vent holes.
Phase II of the repair project required more excavation. This time a bigger, longer trench would be dug
and now it was close to the town. In
fact, the line of the trench went through several houses. Twenty-five families would need to move. Needless to say there were was an
uproar on the part of the citizens of Centralia. Phase II was delayed. Finally, by the end of 1978 the
town decided to go along with the plan, only to find that the Bureau of Mines
had again changed their mind and had a new plan. Once again they were proposing to pump the
area full of water and crushed rock.
Next project management failure – not aligning the project with the
needs of key stakeholders will create delays, conflict, and confusion which
leads to even bigger problems.
The Federal Government Gives Up
Well the story has a tragic ending. While everyone was arguing over what to do,
homes in Centralia were starting to be contaminated with toxic gases from the fire. The government paid to put a carbon monoxide
monitor in each home. Many homes were repeatedly exceeding safe levels. By 1984 the bureau of Mines gave up on controlling the fire. The US congress authorized $42 million to
relocate the remaining residents of Centralia. While
many families took advantage of the buyout, a few families refused to accept the money and
move. In 1992 the government condemned
the entire town and invoked imminent domain.
After years of appeals, the seven remaining residents are allowed to
live out their lives in Centralia, but upon their death their property reverts
to the state.
How The Feds Failed
We have seen the failures on the part of the city and state in the first two blogs in this series. So let’s review the final project management failures made by the Bureau of Mines:
- The project management methodology inhibits projects instead of assisting them.
- Project scope is changed to fit the budget so that a “project success” can be claimed but the scope no longer accomplishes the project goal.
- A refusal by the project team to accept help from others.
- A partial success is hailed as a complete victory and the full project goal is never achieved.
- When in the midst of a crisis, not aligning the project approach with all the stakeholders only deepens the crisis.
One final ironic note about Centralia; it has now become a
tourist attraction. Visitors from around
the world come to see the smoke and steam pouring from the cracks in the roads
and holes in the yards of the abandoned homes.
The town has even been featured on the Travel Channel. Due to the ongoing stream of project
management failures, people all over the world have now heard of Centralia,
Pennsylvania.
References: DeKok, David. Fire Underground: The Ongoing Tragedy of the Centralia
Mine Fire. Guilford, CT: Globe Pequot Press, 2010.